To compute for the overhead rate, we must take the proportion of the total indirect cost over the direct labor cost.
Overhead rate = Indirect Cost/ Direct labor cost
Total projected overhead cost = $2900000+ $800000
=$3700000
Overhead rate= $3700000/$80000
Overhead rate = 46.25The overhead rate of the K company is 46.25