To complete a task in 15 days a company needs 4 people each working for 8 hours per day. the company decides to have 5 people each working for 6 hours per day. assume that each person works are the same rate. how many days will the task take to complete?

Verified Answer :

MannyJ01
MannyJ01 MannyJ01
  • 26-02-2017

it would take 16 days
explanation
if it takes 15 for 4 people to work 8 hours to complete the task, it would be a total of 480 hours. I multiplied 15x4x8. i multiplied 5x6 to get 30. I have to find the third value so i divided 30 from 480 to get 16.

Answer Link

Related Questions

Write the partial fraction decomposition fro the ration expression below 2x 2y 3z 7 x y 5 y 4z 1 1 5x 2x12 2 x3 x2 x 2x4 x2
8 Solve for X 8 is to 64 as 2 is to X
Ms Ramirez wrote a test Part A had truefalse questions each worth 4 points Part B had multiple choice questions each worth 10 points She made the number of poin
Which sentence does NOT belong in a summary of The Ugly Duckling
What is the correct answer
The graph of which of the following inequalities has open circles on 8 and 2 with a line segment between them x 3 lt 5 x 8 lt 2 x 3 lt 5
Would it be correct if I say that freedom was given to us by the government or should I say something else
Solve for 7 and 8 please
There are 22 different amino acids What part of each amino acid is different from the others
If Y2X24X5 what is the value of Y when X 3