the company found that an experienced surveyor can survey a roadbed in 5 hours. An apprentice needs 8 hours to survey the same stretch of road. If the two work together, find how long it takes them to complete the job.

Verified Answer :

MickeyMouseiLover
MickeyMouseiLover MickeyMouseiLover
  • 14-02-2017

40 hours is the answer

Answer Link

Related Questions

What does winning an election by plurality of voters differ from winning by a majority of votes
what is 87771 rounded to the nearest tenth
If someone tells me that scientific knowledge cannot be changed or modified how would I answer that statement
how did the opposition to and subsequent rejection of the league of nations affect US polcie at the beginning of world war two
Which type of essay gives a personal account of the authors feelings on an event
Evaluate this sigma notation equation
Tell me this question very fast
ab c for b help me please this alot of a points please
Which characteristic of postmodern writing is most clearly shown in the two works of tim o brien
At launch the space shuttle weighs 45 million pounds When it is launched from rest it takes 800 s to reach 162kmh and at the end of the first 100 min its speed