Amy, a project manager, needs to make a plan that ensures consistent delivery of the right message to the right people at the right time. Which plan does Amy have to make?


A.) a resource plan

B.) a quality plan

C.) an acceptance plan

D.) a communication plan

Verified Answer :

Anonymous Anonymous
  • 16-01-2017

I would have to say the answer is D.) A communication plan. Hope this helps! :-)

Answer Link

Related Questions

AlMamun founded the House of Wisdom in order to
What are the five food groups recommended by the USDAs MyPlate Food Guidance System A fruits grains oil salt vegetables B fruits grains dairy salt vegetables C
How many of the first 999 Fibonacci numbers are odd
52 Five times a number is 45 53 A number multiple by negative 3 is 12 54 A number divided by 4 is equal to 10 55 The quotient of number and 3 is negative 8 1 Te
The significance of Jefferson Davis in the civil war
What allowed Native Americans in Mexico to settle cities larger than those in areas to the north
What labor conditions and opportunities that we enjoy today appear to have had their roots in World War II
Suppose that Gabe is selling lemonade at a lemonade stand It costs Gabe 20 cents to make each cup of lemonade If Gabe charges 60 cents per cup then 70 people w
Why cant most STIs be transmitted through casual contact with people or contaminated objects
Multiply 4 times 362 using place value and expanded form