Maria's initial project budget was increased from $16,000 to $18,000. What was the variance from the initial budget?

A-12.50%
B88%
C11%
D12.50%

Verified Answer :

Sophlope Sophlope
  • 12-01-2017

the correct answer to the question is d 12.50

Answer Link
omotayoadekoya1 omotayoadekoya1
  • 17-01-2020

Answer:

D. 12.50%

Explanation:

Initial budgeted amount = $16,000

Final budgeted amount = $18,000

Change in amount budgeted  = $18,000 - $16,000 = $2,000

Variance from initial budget is the ratio of the change in the budgeted amount to the initial amount budgeted expressed as a percentage.

Therefore,

Variance = (2000/16000) × 100%

               = 12.5%

Option D. 12.50% is right.

Answer Link

Related Questions

By 30000 BC neanderthals had been replaced by
20 verbos irregulares
presente perfecto Después di qué película has visto recientemente Sofía Paco 1 oir recientemente de Sofía Tenemos que escribir un informe sobre algunas película
An elemental trip through europe
Why do the asbestos roof of house get lifted in hurricane
A colony directly controlled by the English king would be a A Burgesses colony B Crown colony C Catholic colony D Appointed colony
What is a analogy for Astronomer
Lisa draws a circle by tracing a round the botón of a block Which could be the shape of lisas block
In Brown v Board of Education the Supreme Court upheld the doctrine of separate but equal banned segregation in hotels theaters and restaurants declared segrega
On microscopic examination John observed yeast cells dividing into daughter cells What type of asexual reproduction does this represent