Sheria has to evaluate whether she has enough in-house staff working on her project. What steps should she go through to compute this?
AShe should divide up the tasks according to which members are the most productive.
BShe should ask each team member to commit to 20 hours per week and adjust the number of tasks so that they can be completed in that time frame.
CShe should compute number of hours each in-house task on the schedule will take and compare that to the total number of work hours available from her team members.
DShe should compute the number of hours from the schedule starting date to the ending date and divide that by the number of team members.
AShe should divide up the tasks according to which members are the most productive.
BShe should ask each team member to commit to 20 hours per week and adjust the number of tasks so that they can be completed in that time frame.
CShe should compute number of hours each in-house task on the schedule will take and compare that to the total number of work hours available from her team members.
DShe should compute the number of hours from the schedule starting date to the ending date and divide that by the number of team members.