If 6 men can do a piece of work in 14 days, how many men are needed to do the work in 21days?

Verified Answer :

Kunchan
Kunchan Kunchan
  • 11-08-2016

Total work amount
6 men 14 days
84 men days

If it is done within 21 days, need x men
84 men days = x men
 21 days
x = 84/21 men
x = 4 men

Answer Link

Related Questions

The combustion of pentane C5H12 occurs via the reaction C5H12g8O2g5CO2g6H2Og with heat of formation values given by the following table Substance ΔHf kJmol C5H1
1 is 5 of what number
Write the expression in the form abi35i22i
23 Completa el cuadro con las características de la fotosíntesisy la respiración celularCaracterísticasDónde ocurreFotosíntesisEn las plantasQué sustancias requ
Where is the BIOS for your computer located A Within the CPU B In the PSU C In the motherboard D In the optical drive
The occurrence of Kristallnacht or the Night of Broken Glass in Germany in 1938 showed that the Nazi government fully supported violence against Jews needed mor
Is aminalia unicellular or multicellular
Creating a monoculture can be a downside to GMOs because they cant grow in salty soils a disease can destroy everything planting one crop saves time Bees avoid
Find the length of the hypotenuse of a right triangle if a 9 and b 12 A 105 B 15 C 165 D 21
describe the steps you take to order 585 on top 8 on bottom fraction 08 353 on top