Incident managers begin planning for the demobilization process:

Awhen incident activities shift from response to recovery.
Bright before the first resources are ready to be released.
Cas soon as possible to facilitate accountability of the resources.
Dafter being requested by the emergency operations center.

Verified Answer :

Hagrid

The correct answer to this question is letter "c. as soon as possible to facilitate accountability of the resources." Incident managers begin planning for the demobilization process as soon as possible to facilitate accountability of the resources.