It takes 4000 persons hours to complete a project. How many weeks will it take a team of 5 people to complete the project if each person works 8 hours a day, 5 days a week?

Verified Answer :

Etrade Etrade
  • 02-05-2016

4000/5 people = 800 hours per person.
5x8 = 40 hours a week per person
40x5 people = 200 hours a week with all 5 people working.
800/200 = 4 weeks
The answer is 4 weeks

Answer Link

Related Questions

Which of the following statements is true with regard to Pakistan A US sanctions imposed on Pakistan after its nuclear tests were dropped in late 2001 B General
What evidence does McCarthy provide to support his claims of Communists in the State Department
3596 Evaluate what the total score
How did dictators come to power during ww2
All of the following are generally human causes of deforestation except urban use forest fires logging creation of pasture for cattle
Jeremy drew a polygon with four right angles and four sides with the same length Name all the polygons that he could have drawn
An isotope of which element has an atomic number of 6 and a mass number of 14
What is the nearest thousand hundreds tens for 7931
The tripod joint has a spider with three trunnions a Trueb False
What was the name of the newspaper that William Lloyd Garrison published in order to spread his antislavery ideas The Democratic Review The Pennsylvania Gazette