A project that costs $2,100 to install will provide annual cash flows of $540 for the next five years. The firm accepts projects with payback periods of less than four years.
AWhat is this project's payback period? (Note: Round your answer to 3 decimal places.)
BWill the project be accepted?
c-1. What is the project's NPV if the discount rate is 3%? (Note: A negative amount should be indicated by a minus sign. Do not round intermediate calculations. Round your answer to 2 decimal places.)
c-2. Should this project be pursued?
d-1. What is the project's NPV if the discount rate is 10%? (Note: A negative amount should be indicated by a minus sign. Do not round intermediate calculations. Round your answer to 2 decimal places.)
d-2. Should this project be pursued?
EWill the firm's decision change as the discount rate changes?
a. Payback periodYears
b. Will the project be accepted?
c-1. NPV of the project if the discount rate is 3\%
c-2. Should this project be pursued?
d-1. NPV of the project if the discount rate is 10\%
d-2. Should this project be pursued?
e. Will the firm's decision change as the discount rate changes?
AWhat is this project's payback period? (Note: Round your answer to 3 decimal places.)
BWill the project be accepted?
c-2. Should this project be pursued?
d-1. What is the project's NPV if the discount rate is 10%? (Note: A negative amount should be indicated by a minus sign. Do not round intermediate calculations. Round your answer to 2 decimal places.)
d-2. Should this project be pursued?
EWill the firm's decision change as the discount rate changes?
a. Payback period | Years |
b. Will the project be accepted? | |
c-1. NPV of the project if the discount rate is 3\% | |
c-2. Should this project be pursued? | |
d-1. NPV of the project if the discount rate is 10\% | |
d-2. Should this project be pursued? | |
e. Will the firm's decision change as the discount rate changes? | |