A manufacturer of solid state drives (SSDs) has projected the next six months of demand to be as shown the table below:



Supply/Demand Info Beginning Jan Feb Mar Apr May Jun

Forecast (demand) 52,200 48,000 53,800 62,000 53,400 56,000

Regular production

Overtime production

Subcontract production

Ending inventory 7,000

Hired employees

Fired employees

Total employees 190



Cost variables are as follows:



Cost Variables

Labor cost/hour $20

Overtime cost/unit $31

Subcontracting cost/unit $29

Holding cost/unit/month $10

Hiring cost/employee $3,500

Firing cost/employee $5,100



Here is some additional relevant (capacity) information:



Capacity Information

Total labor hours/SSD 2

Regular production units/employee/month 200

Max regular production/month 56,600

Max overtime production/month 4,800

Max subcontractor production/month 4,600



Assuming the company uses regular production first, then ONLY overtime and/or subcontract production, answer the following questions:



What is the regular production cost (over the six months from January through June) for a CHASE production plan? (Display your answer to the nearest whole number.)



Number





What is the total overtime production cost for this production plan? (Display your answer to the nearest whole number.)



Number





What is the total subcontract cost for this production plan? (Display your answer to the nearest whole number.)



Number





What is the total holding cost for this production plan? (Display your answer to the nearest whole number.)



0





What is the total hire cost for this production plan? (Display your answer to the nearest whole number.)



Number





What is the total fire cost for this production plan? (Display your answer to the nearest whole number.)



Number





What is the total cost (sum of all costs) for this production plan? (Display your answer to the nearest whole number.)



Number