The Company has a problem. Tom. Who was in charge of a critical control account, Quit and destroyed most of his cost records. All that could be salvaged were the following bits of information.
BAC=120000
Cumulative earned value 40000,
cumulative cost variance=-10000,
cumulative schedule variance=1000,
estimate to complete=86000.
Help reconstruct the status of tom's control account by determining the following items.
APercent Complete
BBudget (Cumulative)
CActuals (Cumulative)
DEAC
EVariance at Completion
F. CPI
G. TCPI
H. Calculate a projected EAC using the standard independent EAC formula of EAC=AC+ETC, where ETC=Work Remaining/CPI
BAC=120000
Cumulative earned value 40000,
cumulative cost variance=-10000,
cumulative schedule variance=1000,
estimate to complete=86000.
Help reconstruct the status of tom's control account by determining the following items.
APercent Complete
BBudget (Cumulative)
CActuals (Cumulative)
DEAC
EVariance at Completion
G. TCPI
H. Calculate a projected EAC using the standard independent EAC formula of EAC=AC+ETC, where ETC=Work Remaining/CPI